    Build prime cost and full production cost

    Does a cabinet's KHR 30,000 production overhead belong in its prime cost?

    • TQ3-C01-L13
    • About 2 min
    • Khmer voice · English terms
    • Textbook pp 23–25
    Subtitles
    Speed
    Audio: Khmer

    Lesson 13 · 14 of 16 in TQ3 Chapter 1

    Practice card

    Your turn

    Production overhead is KHR 45,000; the direct costs are unchanged. What are prime cost and full production cost?

    Decide your answer first, then check it.

    Check yourself

    3 exam-style questions

    2 questions on this lesson and 1 review question from Lesson 11. Choose an answer, then check it to see why it is right or wrong.

    1. Question 1 of 3This lessonTextbook pp 23–25
      Direct materials are KHR 70,000, direct labour KHR 50,000 and a traceable direct expense KHR 10,000. What is prime cost?

    2. Question 2 of 3This lessonTextbook pp 23–25
      How does a product's full production cost relate to prime cost?

    3. Question 3 of 3Review · Lesson 11Textbook p 20
      A stepped cost has a flat band followed by a jump. What causes the jump?

    Your answers stay on this device. A question you miss goes on your review list and comes back in a later quiz.

    Notes

    Read first: TQ3 study text, printed pages 23–25 (Khmer edition pages 30, 32–33).

    §§4.2–4.4 pp 23–25. The book's per-unit schedules (pp 23, 25) are symbolic; its only prime-cost figures are the period totals on p 15: raw materials consumed KHRm 155,000 + manufacturing wages 100,000 = prime cost 255,000, + production overheads 162,000 = manufacturing costs 417,000 (L07). The cabinet case is ours, in KHR, because the exam asks for the prime cost of a cost unit (p 3). Its direct expense is a sub-contractor's fee, the book's own kind of direct expense (p 23), which is uncommon in manufacturing (p 23). Inexpensive traceable materials may be treated as indirect where measuring them is not worthwhile (p 24).

    How this lesson uses the textbook: TQ3 Chapter 1 · English pp 23–25 · Khmer pp 30, 32–33

    Source: TQ3 Chapter 1 · English printed pp 23–25 · Khmer printed pp 30, 32–33

    These lessons add to your formal studies; they don't replace them. Keep going to class, reading your textbook, doing the practice exercises and taking notes.

    Read the English transcript

    Does a cabinet's thirty thousand riels production overhead belong in its prime cost?

    No: prime cost contains direct costs only; production overhead is added for full production cost.

    Prime cost groups the costs traced directly to a cost unit. For example, timber and the labour shaping it can be direct to furniture, while a shared factory cost needs an overhead basis. Specify the boundary of any full-cost measure. The book's full cost of sale adds administration and selling and distribution overheads, so it is a broader measure than full production cost.

    Our cabinet uses direct materials of sixty thousand riels, direct labour of forty thousand, and a carving sub-contractor's fee of twenty thousand, a direct expense. Add them: prime cost is one hundred and twenty thousand riels. Its share of production overhead is thirty thousand, giving full production cost of one hundred and fifty thousand riels. Show both subtotals separately, and check the overhead is not already inside the direct figures.

    Watch out for adding selling or administration costs into a subtotal labelled full production cost.

    Your turn. Change only the production overhead share to forty-five thousand riels. What are prime cost and full production cost? Decide, then check your practice card.

    Remember to build the direct subtotal first and add only the overhead relevant to the named boundary.